What would be the implications if we cancel the Approval Cycle mid-way?

0
0

Suppose we cancel the approval cycle mid-way, that is when a few approvers have approved and few have not – What will be the implications? Will all approvers receive notification that it has been cancelled?

RESOLVED
Marked as spam
Posted by
Asked on 26 January 2021 5:33 am
258 views
Public question
0
Private answer

If the approval cycle is cancelled midway, that is a few approvers have approved and a few have it still pending - The status of the object will change to 'Approval Cycle Cancelled'.All the approvals which have already been completed will be nullified. Hence, the User will have to retrigger the approval cycle after making the changes he desires. In this scenario, all the Approvers will once again have to approve/reject from scratch.

Marked as spam
Posted by
Answered on 30 March 2021 7:26 am